Ms Santosh Stone Industries Through Its One Of The Partners Smt Shanti Singh vs. Eastern Railway Through Its Divisional Railway Manager
Held
The Court held that the petitioner's deposit of the license fee for the year 2019-20 only entitled them to avail the benefit of the license up to 31.03.2020. Since the impugned cancellation order was passed on 11.08.2020, by which date the petitioner admittedly had no right to continue occupying the plot from 1st April 2020 onwards, the order passed by the authority did not require any interference. The Court noted that the renewal of the license was subject to the execution of a fresh agreement, a copy of which was not produced by the petitioner, indicating it had not been executed. Therefore, the Court found no grounds to interfere with the cancellation order.
Facts
The petitioner, M/s Santosh Stone Industries, a partnership firm, filed a writ petition challenging a letter dated 11.08.2020 issued by the Divisional Commercial Manager, Eastern Railway, Malda Division, which cancelled the license granted to the petitioner to use and occupy plot no.1 at Sawai Siding of Sakrigali Station. The petitioner had been occupying the plot since 1986 under various agreements, with the license being renewed periodically upon deposit of annual license fees. The renewal for 2019-20, subject to a fee of Rs. 11038/- plus GST of Rs. 1987/-, was deposited by the petitioner on 18.10.2019. The petitioner also possessed valid licenses from other government departments to run its business. The petitioner sought quashing of the cancellation order and restoration of the license.
Key Issues
1. Whether the cancellation of the license granted to the petitioner to use and occupy plot no.1 at Sawai Siding of Sakrigali Station by the Divisional Commercial Manager, Eastern Railway, Malda Division, vide letter dated 11.08.2020, is bad in law and liable to be quashed. Petitioner's Contention: The petitioner argued that the cancellation order was bad in law because they had deposited the license fee for the year 2019-20, including GST, and possessed valid licenses from other departments. They contended that the action taken by the respondents was prejudicial to their interests. Respondents' Contention: The respondents (Eastern Railway) did not explicitly file a counter-argument in the provided text. However, the Court's reasoning implies that the renewal of the license was conditional upon the execution of a fresh agreement, which had not been completed by the petitioner.
Sections Cited
None explicitly mentioned as being discussed or relied upon in the judgment text provided.
AI-generated summary — verify with the full judgment below
IN THE HIGH COURT OF JHARKHAND AT RANCHI (Civil Writ Jurisdiction) WP(C) No. 3898 of 2020
M/s Santosh Stone Industries ….. ...... Petitioner Versus Estern Railway & Ors.
…. …. Respondents
------ CORAM : HON’BLE MR. JUSTICE KAILASH PRASAD DEO
------- For the Petitioner : Mr. Pankaj Srivastava, Advocate For the Respondents/Railways :Mr. Vikash Kumar, Advocate
-------- The matter is being taken up through Video Conferencing. Learned counsel for the parties have no objection with it and submitted that audio and video qualities are good. Order No.07 /Dated: 18
th November, 2022 Heard, learned counsel for the petitioner, Mr. Pankaj Srivastava and learned counsel for the respondents/Railways, Mr. Vikash Kumar. The petitioner, M/s Santosh Stone Industries, a partnership firm, having its address as Sakrigali Junction, P.O.-Sakrigali Junction, P
The judgment continues below.
Read the full judgment
A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.
The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.
Reproduced from the public record of the Jharkhand High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.