Gautam Coal Works Private Limited Through Its Managing Director Manendra Kumar Singh vs. The Central Coalfields LTD Through Its Chairman Cum Managing Director
Held
The Court held that the termination of the Fuel Supply Agreement (FSA) by CCL was not arbitrary, illogical, or perverse and was a probable view. The Court found that the impugned order was well-reasoned and supported by documentary evidence. Specific discrepancies noted included vehicles used for dispatch being identified as cars and motorcycles when they were trucks, the same vehicle number being used for different types of vehicles on different dates, multiple dispatches to various firms on the same date by one vehicle, and mismatches between GST invoices and sale register vehicle numbers. Variations in electricity consumption and billed units were also considered, along with the lack of documentary proof for protests to the electricity department. Irregularities in worker engagement and statutory forms, with discrepancies between attendance sheets and PF/ESI challans, further supported the conclusion that coal was being diverted. The Court also noted that physical inspection was not mandatory and, in this case, would have served no useful purpose as the factory had been closed for four years. As the termination order was upheld, the Court found no occasion to direct the refund of the security deposit. The writ petition was dismissed.
Facts
The petitioner, Gautam Coal Works Private Limited, challenged an office order dated 28.5.2022 by Central Coalfields Limited (CCL) terminating their Fuel Supply Agreement (FSA) dated 30.4.2008 and forfeiting the security deposit. The FSA was entered into pursuant to Coal India Limited's 2007 policy. Following a survey by the Income Tax Department alleging the petitioner could only process 0.05% of the coal supplied, CCL suspended supply. After several representations, clarifications, and resolutions by the Regional Economic Intelligence Council (REIC), the Income Tax Department directed CCL to suspend supply, leading to termination of the FSA. Previous writ petitions resulted in directions for independent inquiries and physical verification. The impugned order reiterated the termination and forfeiture, citing diversion of coal.
Key Issues
1. Whether the termination of the Fuel Supply Agreement (FSA) by CCL is arbitrary and mala fide, ignoring the terms of the FSA and previous court directions, particularly Clause 4.4 of the FSA? (Petitioner's contention: Yes, CCL acted arbitrarily and malafide, ignoring previous court orders and the functional status of the unit certified by the Directorate of Industries. They argued that discrepancies in vehicle numbers were human error and that electricity consumption variations were due to using private generators. The reasons for rejection were non-existent. Revenue/State (CCL) contention: Not recorded explicitly, but implied by their defense of the termination order. The judgment indicates CCL argued that the petitioner was diverting coal based on analysis of documents and discrepancies found.) 2. Whether the petitioner is entitled to the refund of the security deposit if the termination of the FSA is found to be unjust? (Petitioner's contention: Yes, if termination is unjust, the security deposit should be refunded. Revenue/State (CCL) contention: Not recorded explicitly, but their defense of the termination implies they are entitled to forfeit the deposit.)
Sections Cited
Section 133A(2A)
AI-generated summary — verify with the full judgment below
1
IN THE HIGH COURT OF JHARKHAND AT RANCHI W.P.(C) No. 2818 of 2022 Gautam Coal Works Private Limited, a company incorporated under the Companies Act, 1956, having its Industrial Unit at Tape, Ormanjhi, Ranchi through its Managing Director, Manendra Kumar Singh son of Mithilesh Kumar Singh, resident of Flat No.403-B, Ganesh Apartment, Ashok Vihar, PO PS Argora, District Ranchi.
... Petitioner. -Versus-
Central Coalfields Limited (CCL), through the Chairman-cum- Managing Director, Darbhanga House, Gonda, Ranchi.
The Chairman-cum-Managing Director, CCL, Darbhanga House, Gonda, Ranchi.
The General Manager (Marketing and Sales), CCL, Darbhanga House, Gonda, Ranchi.
… Respondents CORAM : SRI SANJAYA KUMAR MISHRA, C.J.
SRI ANANDA SEN, J.
----- For the Petitioner : Mr. Vimal Kirti Singh, Sr. Advocate. For Respondent- CCL: Mr. Amit Kumar Das, Advocate. ----- C.A.V. On 08.12.2023
Pronounced on: 21 / 12 /2023 J U D G M E N T Per Ananda Sen, J.
In this writ petition, the petitioner has prayed for quashing the office order dated 28.5.2022 contained in reference No. CCL/HQ/C-4/2022-23/1142 (Annexure-1
The judgment continues below.
Read the full judgment
A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.
The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.
Reproduced from the public record of the Jharkhand High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.