Clean Coal Enterprises PVT LTD vs. Central Coalfields LTD, Through Its Chairman Cum Managing Director

WPC/4859/2024HC JharkhandGSTCNR JHHC01029371202417 September 2024Bench: HON'BLE THE ACTING CHIEF JUSTICE,HON'BLE MR. JUSTICE SANJAY KUMAR DWIVEDI39 pages
AI SummaryDismissed

Held

The Court held that the petitioner's technical bid was rightly rejected due to its failure to comply with the conditions stipulated in the bid document, specifically the timeline for submitting clarifications. The Court reasoned that the petitioner admitted to negligence in not checking the portal and responding within the stipulated time. Citing the Supreme Court's decision in Sorath Builders Vrs. Shreejikrupa Buildcon Limited & Anr., the Court emphasized that a party cannot be allowed to take advantage of its own wrong and that tender conditions must be strictly adhered to. The Court found no error in the decision-making process by CCL. The argument regarding the price quoted by the successful bidder was deemed a consequence to be considered only after technical bids were successfully evaluated. Therefore, no positive direction could be passed in favour of the petitioner.

Facts

The petitioner, Clean Coal Enterprises Pvt. Ltd. (lead member of a consortium), challenged the rejection of its technical bid for a coal washery plant tender issued by Central Coalfields Ltd. (CCL). CCL had sought clarifications from the petitioner on 26.07.2024, with a deadline of 02.08.2024. The petitioner failed to respond by the deadline, citing relocation of its office and inadvertent non-checking of the e-procurement portal. The petitioner submitted its response via email on 02.08.2024, requesting an extension, but this was not accepted. Subsequently, the petitioner's technical bid was rejected via email on 29.08.2024. The petitioner sought to amend its writ petition to include a challenge to this rejection, which was allowed. The petitioner argued that the clarifications sought did not affect its eligibility and were submitted on the last date. The respondents did not object to the amendment.

Key Issues

1. Whether the rejection of the petitioner's technical bid by the Respondent-CCL is arbitrary, unreasonable, and violative of Articles 14 and 19(1)(g) of the Constitution of India, considering the petitioner's submission of clarifications on the last date and the nature of the clarifications sought. Petitioner's arguments: The petitioner contended that the clarifications sought by CCL did not affect its eligibility status and were submitted on the last date for clarifications. They argued that the rejection was unreasoned, arbitrary, and unreasonable, violating constitutional rights. They also pointed to the potential for a higher price quoted by the successful bidder as a ground for reconsideration. Revenue/State's arguments: The respondent-CCL did not raise specific arguments against the petitioner's claims in the provided text, but the court's reasoning implies that the petitioner's failure to adhere to the stipulated timeline for submitting clarifications was a critical factor. The court relied on established legal principles regarding adherence to tender conditions.

Sections Cited

Article 14, Article 19(1)(g)

AI-generated summary — verify with the full judgment below

1 WPC No.4859/2024

IN THE HIGH COURT OF JHARKHAND AT RANCHI W.P.(C) No.4859 of 2024

With

I.A. No.9378 of 2024

------ Clean Coal Enterprises Pvt. Ltd., (Lead Member of Consortium of Clean Coal Enterprises Pvt. Ltd., Maa Durga Coal and Minerals Pvt. Ltd., and Rama Coal Washeries Pvt. Ltd.) having its registered office at Commercial Building, Rama World, Tifra Parsada, Bilaspur, P.O. and P.S. Bilaspur Industrial Estate, District - Bilaspur, Chhattisgarh 495 001, through its General Manager (Marketing) and Authorised representative, Mr. Santosh Kumar Soni, aged about 50 years, son of Mr. Ram Gopal Soni, resident of Sankalp, behind Bachpan School, Mahavir Nagar, P.O. and P.S. - Mahavir Nagar, District - Bilaspur, Chhattisgarh 495001. …. …. Petitioner

Versus

1.

Central Coalfields Ltd., through its Chairman cum Managing Director, having its office at Darbhanga House, P.O. - Court Post Office, P.S. Kotwali, District Ranchi, Jharkhand 834001. 2. General Manager (Washery Construction), Central Coalfields Ltd., having its office at Darbhanga House, P.O. - Court Post

The judgment continues below.

Read the full judgment

A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.

See plans and prices

The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.

Reproduced from the public record of the Jharkhand High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.