National Management Training Institute vs. State Of Maharashtra
Original PDF →Facts
The Petitioner, M/s. Food Safety Services, challenged the rejection of its technical bid for a tender floated by the Directorate of Primary Education (Respondent No. 2) for training cooks and helpers under the Mid-Day Meal Scheme. The tender required bidders to submit various documents, including GSTR 1 and GSTR 3B, audited balance sheets, and CA turnover certificates. The Petitioner's bid was rejected on March 29, 2023, with the reason cited being the absence of UDIN on each page of the submitted documents. The Petitioner contended that this was not a stipulated requirement and that Respondent No. 3, Shree Analytical Testing and Research Laboratory, whose bid was accepted, suffered from a conflict of interest and lacked necessary experience. The Petitioner had previously filed a writ petition before the Nagpur Bench, which was dismissed on jurisdictional grounds on May 3, 2023. Subsequently, a work order was issued to Respondent No. 3 on May 4, 2023. A contempt petition was also filed alleging disobedience of a previous order dated April 25, 2023, in a related writ petition.
Held
The Court held that the writ court should refrain from interfering with the decision-making process of the tendering authority, especially when the work has already been accomplished and payments disbursed. The Court noted that its scope of judicial review is limited to examining the decision-making process for arbitrariness, irrationality, unreasonableness, bias, or malafides, none of which were found to be present. The Petitioner's challenge based on the alleged infraction of clause 4.4.3.1 of the Government Resolution was also dismissed, as the clause pertains to the minimum number of bidders required for a tender to be competent. In this case, five bids were received, but only one qualified technically. The Court found no willful breach of the order dated April 25, 2023, in the contempt petition, based on the affidavits filed by the Respondents. Therefore, the Writ Petition was disposed of, leaving it open for the Petitioner to seek compensation from the appropriate forum, and the Contempt Petition was dismissed.
Key Issues
1. Whether the rejection of the Petitioner's technical bid was arbitrary and without proper justification, violating the tender conditions and principles of natural justice? 2. Whether Respondent No. 3's technical bid was wrongly accepted due to a conflict of interest and lack of State-level experience, as alleged by the Petitioner? 3. Whether the Respondents acted in undue haste in issuing the work order to Respondent No. 3 immediately after the dismissal of the Petitioner's earlier writ petition? 4. Whether the Respondents willfully breached the order dated April 25, 2023, warranting contempt proceedings? Petitioner's Arguments: The Petitioner argued that the rejection of its bid was improper as no reasons were disclosed initially and the stated reason (lack of UDIN on each page) was not a mandatory requirement of the tender. It was contended that Respondent No. 3 had a conflict of interest as it was both a mid-day meal caterer and a testing agency involved in the same scheme, and its technical bid was flawed. The Petitioner also highlighted the undue haste in issuing the work order post-dismissal of its earlier petition. Reliance was placed on the Government Resolution dated December 1, 2016, regarding office procedures for procurement. Respondents' Arguments: The State Authorities argued that the Petitioner failed to qualify the technical criteria, and its bid was rejected accordingly. They contended that since the work has been awarded and implemented by Respondent No. 3, the Petitioner's remedy lies in claiming damages for alleged breach of tender terms or violation of rules. They relied on a previous judgment of the High Court in WP No. 5420/2023, which declined interference in a similar tender process. Regarding the contempt petition, the Respondents denied any deliberate or willful breach of the court's order.
Sections Cited
Section 4.4.3.1
AI-generated summary — verify with the full judgment below
Cause title — parties, addresses and appearances
the said order. In addition, it also submission of Mr. Naphade that rejection of the technical bid of the Petitioner is also erroneous since the index of its bid clearly indicate that audited balance-sheet for the financial year 2021- 2022 was annexed therewith and it even indicated the UDIN being 23185882 BGYVGZ5254. By referring to the Affidavit in Reply filed by Respondent No.2, Mr. Naphade would submit that there is no denial of the Petitioner’s assertion in the Petition that Audited balance-sheets were duly submitted with the UDIN.
The Additional Government Pleader representing Respondent Nos.1 and 2 would rely upon the Affidavit filed, traversing the pleading in the Petition and he would submit that the Petitioner was one of the bidders in the Expression of Interest (EOI), but it could not qualify the technical criteria and, therefore, its bid was rejected and as of now when the work is awarded to Respondent No.3, who has already 7/10
17-CP-255-2023.doc implemented the work, the only remedy available to the Petitioner is to claim damages for the alleged breach of the terms of the Tender or the alleged violation of the Rules formulated governing the tender process. Reliance is placed upon the decision delivered by this Court in WP No.5420/2023 filed by National Management Training Institute vs. State of Maharashtra & Others, which had refused to entertain the objection pressed and no interference was shown in the tender process. The learned Additional Government Pleader has placed before us a Chart reflecting the districts in which the training was imparted in furtherance of the work order issued in favour of Respondent No.3 and this include 35 districts and we are informed that training is provided to 132909 cooks/helpers under the Mid-day Meal Scheme and a sum of Rs.7,24,69,800/- is disbursed in favour of Respondent No.3. 11. In the wake of the aforesaid development, which is brought to our notice, we understand the futility of entertaining the challenge in the Petition as the work allotted to Respondent No.3 is already accomplished and the payment is already disbursed in its favour. The rejection of the technical bid of the Petitioner was on the ground that it did not comply with the requisite conditions and it being a well settled position in law that the writ court shall refrain itself from imposing its decision over the decision of the Tendering Authority, as to whether or not to accept the bid, since this Court do not possess any expertise to examine the niceties of the terms and conditions in the wake of several activities being carried out by the State. In N.J. Projects Ltd. vs. Vinod Kumar Jain & Ors.1 the Apex Court observed thus : 1 (2022)6 SCC 127 8/10
17-CP-255-2023.doc “23.
In view of the above judgments of this Court, the writ court should refrain itself from imposing its decision over the decision of the employer as to whether or not to accept the bid of a tenderer. The Court does not have the expertise to examine the terms and conditions of the present day economic activities of the State and this limitation should be kept in view. Courts should be even more reluctant in interfering with contracts involving technical issues as there is a requirement of the necessary expertise to adjudicate upon such issues. The approach of the Court should be not to find fault with magnifying glass in its hands, rather the Court should examine as to whether the decision-making process is after complying with the procedure contemplated by the tender conditions. If the Court finds that there is total arbitrariness or that the tender has been granted in a mala fide manner, still the Court should refrain from interfering in the grant of tender but instead relegate the parties to seek damages for the wrongful exclusion rather than to injunct the execution of the contract. The injunction or interference in the tender leads to additional costs on the State and is also against public interest. Therefore, the State and its citizens suffer twice, firstly by paying escalation costs and secondly, by being deprived of the infrastructure for which the present day Governments are expected to work.”
It being a settled position that it is not the decision of the Tendering Authority, which is subject to examination in exercise of the powers of judicial review, but the limited scope available is to examine the decision making process. The scope of judicial review of an administrative action in a manner relating to tender/award of contract is very minimal and exercise of the power of judicial review is permitted only when it is intended to prevent arbitrariness, irrationality, unreasonableness or the action is actuated with bias and malafides. We do not find any such element present, which would warrant our interference . The only ground on which the Petitioner has called in question, the decision making process of Respondent No.2 is infraction of clause 4.4.3. 1. When we adverted our attention to the said clause, even this challenge must fall as the said clause contemplate that minimum three bidders are required to make the tender competent and if less than three bidders take part, extension of one week should be granted on two occasions, but not thereafter. 9/10
17-CP-255-2023.doc
In this case, there were five bids received, of which only one has technically qualified and considering the nature of the project, the work was allotted in favour of the said bidder, who has now even accomplished the task assigned to it. In the wake of aforesaid circumstances, Writ Petition before us at this point of time do not deserve any consideration, and leaving it open to the Petitioner to seek compensation by approaching the appropriate forum, we deem it appropriate to dispose of the Writ Petition.
As far as Contempt Petition, alleging disobedience of the order passed by the Division Bench of this Court on 25/04/2023 is concerned, we have perused the Affidavit filed on behalf of Respondent Nos.1 and 2 and on its reading we are unable to be persuaded by the fact that there is deliberate or willful breach of the directions issued by this Court on 25.04.2023. For this reason, we decline to entertain the Contempt Petition and drop the proceedings. (BHARATI DANGRE, J.) (CHIEF JUSTICE) 10/10
Reproduced from the public record of the Bombay High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.