Kumar Urban Development Private Limited, Pune And Anr. vs. Atul Ashok Chordia And Anr.

IA/770/2023HC BombayGSTCNR HCBM01003550202308 March 2023Bench: HON'BLE SHRI JUSTICE MANISH PITALE36 pages
AI SummaryDismissed

Facts

The Appellants are aggrieved by an order of the District Court rejecting their application under Section 9 of the Arbitration and Conciliation Act, 1996, for interim measures. The dispute arises from a Share Purchase Agreement dated March 21, 2018, where Appellants agreed to sell 100% equity shares of Respondent No. 3 (then KUL Developers Private Limited) to Respondent Nos. 1 and 2. A significant portion of the consideration was reserved for an access road. Disputes arose concerning the construction of this access road and the payment of consideration. Appellants claimed the road was complete and sought payment of Rs. 25 Crores or allotment of flats as per Clause 9.2 of the agreement. Respondents contended the road was not completed as per schedule. Appellants apprehended that Respondents were disposing of project flats, jeopardizing their option to claim consideration via flats.

Held

The Court held that the Appellants failed to make out a prima facie case for the grant of interim measures. The Court found that the Appellants' communications, particularly dated February 3, 2020, July 30, 2020, and August 1, 2021, prima facie indicated they had exercised the option of demanding monetary compensation of Rs. 25 Crores. Their subsequent reference to the option of seeking consideration via allotment of project flats in a letter dated October 14, 2021, demonstrated a conduct of 'approbating and reprobating,' meaning they were taking inconsistent positions. The Court relied on the principle that a party cannot blow hot and cold simultaneously to benefit from an agreement. The District Court's rejection of the application was deemed not an error, as it was a possible view based on the facts. The Court noted that a cheque for Rs. 25 Crores held by an Escrow Agent sufficiently secured the Appellants' interests. The Court directed the Respondents to deposit a fresh undated cheque for Rs. 25 Crores with the Escrow Agent within four weeks.

Key Issues

1. Whether the Appellants made out a prima facie case for the grant of interim measures, specifically restraining the Respondents from selling, alienating, or creating third-party rights in project flats and sales shares, pending arbitration? The Appellants argued that they were entitled to interim measures to prevent Respondents from disposing of project flats, thereby foreclosing their option under Clause 9.2 of the agreement to claim consideration by allotment of flats. They contended that the Respondents' actions would deprive them of exercising this option. The Respondents argued that the Appellants had already exercised their option by demanding monetary consideration of Rs. 25 Crores, and their subsequent attempt to claim flats constituted 'approbating and reprobating' (blowing hot and cold), disentitling them to equitable relief. They also contended that the Appellants had failed to complete their obligations regarding the access road.

Sections Cited

Section 9

AI-generated summary — verify with the full judgment below

C-ARA.10.2023.doc IN THE HIGH COURT OF JUDICATURE AT BOMBAY CIVIL APPELLATE JURI ICTION ARBITRATION APPEAL NO. 10 OF 2023 WITH INTERIM APPLICATION NO. 770 OF 2023 IN ARBITRATION APPEAL NO. 10 OF 2023 Kumar Urban Development Private Limited & Anr. ...Applicants/Appellants Versus Atul Ashok Chordia & Ors. ...Respondents ***  Dr. Veerendra Tulzapurkar, Senior Advocate a/w Mr. Aditya Shiralkar, Mr. Gaurav Gopal and Mr. Kanu Upadhyay i/by Wadia Ghandy & Co., for Applicants/Appellants.  Mr. Mayur Khandeparkar, Mr. Akshay Doctor and Mr. Parag Sawant i/by P.S. Chambers, for the Respondents. *** CORAM : MANISH PITALE, J DATE : 08th MARCH, 2023 P. C. :

1.

Heard finally with the consent of the learned Counsel for the parties.

2.

The Appellants are aggrieved by judgment and order dated 06th January, 2023, passed by the Court of Additional Sessions Judge, Pune (hereinafter referred to as the “District Court”) in an application filed by the Appellants under Section 9 of the Arbitration and Conciliation Act, 1996, for grant of interim measures. By the impugned judgment and order, the District Court rejected the said application. Shrikant SHRIKANT SHRINIV

The judgment continues below.

Read the full judgment

A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.

See plans and prices

The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.

Reproduced from the public record of the Bombay High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.