Keshkal G.N. INDIA Bauxite Mines And Minerals Limited vs. State Of Chhattisgarh
Held
The Court held that the petitioner is not entitled to any relief. On the first issue, the Court found that the doctrine of promissory estoppel is not available against the Government when it exercises its statutory or sovereign functions, or when its officers act outside the scope of their authority. The Court cited several Supreme Court judgments to establish that assurances given by government officials cannot bar the government from enforcing statutory prohibitions or acting in public interest. The amendments to the MMDR Act, 1957, and the introduction of GST, which altered the statutory regime, further weakened the petitioner's claim based on prior assurances. Regarding the second issue, the Court implicitly rejected the argument that the area remained reserved, as the entire petition was dismissed. The Court concluded that the petitioner's claim based on promissory estoppel was without substance and that the writ petition was devoid of merit. Therefore, the petition was dismissed.
Facts
The petitioner, Keshkal G.N. India Bauxite Mines and Minerals Limited (J.V.C.), filed a writ petition seeking directions for the Chhattisgarh Mineral Development Corporation Limited (CMDC) to decide its application for a mining lease. The petitioner also sought to ensure their application remained alive and that the area reserved in 1981 for public sector undertakings for Bauxite mining would continue to be so reserved, despite amendments to the Mines and Minerals (Development & Regulation) Act, 1957 (MMDR Act). The dispute stems from a 1981 notification reserving Bauxite mining rights for MPSMC, subsequent joint venture agreements between CMDC and the petitioner, and various rejections of mining lease applications by the Union of India due to non-compliance with statutory provisions and guidelines, particularly after the MMDR Amendment Act, 2015. The petitioner argued based on promissory estoppel and assurances given by government authorities.
Key Issues
1. Whether the petitioner is entitled to a direction for the respondent authorities to decide the application submitted by respondent No. 2 (CMDC) for grant of mining lease, and if not decided, whether the application should be treated as eligible and remain alive in view of Section 17(A)(2a) of the MMDR Act, 1957? (Question of law and mixed fact and law) 2. Whether the area reserved in 1981 for public sector undertakings for mining of Bauxite remains reserved even after amendments to the MMDR Act, 1957? (Question of law) Petitioner's arguments: The petitioner contended that the State Government's actions and assurances created a legitimate expectation and that the principle of promissory estoppel should apply, preventing the respondents from resiling from their promises. They relied on the judgment in Monet Ispat and Energy Limited Vs. Union of India & others. They argued that the area should remain reserved for public sector undertakings as per the original reservation. Respondents' arguments: The State and Union of India argued that promissory estoppel cannot be invoked against the Government when exercising its statutory or sovereign functions, citing various Supreme Court judgments like The Bihar Eastern Gangetic Fishermen Co-operative Society Ltd. vs. Sipahi Singh and others, and M/s Jit Ram Shiv Kumar and others vs. State of Haryana and others. They asserted that the amendments to the MMDR Act, 1957, particularly Section 174(2)(c) of the CGST Act, superseded any prior assurances or policies.
Sections Cited
Section 17(A)(2a), Section 11(3), Section 10A, Section 10(2A), Section 174(2)(c)
AI-generated summary — verify with the full judgment below
2025:CGHC:51600
AFR HIGH COURT OF CHHATTISGARH AT BILASPUR WPC No. 1142 of 2023 Reserved on : 17.07.2025 Delivered on : 16.10.2025 Keshkal G.N. India Bauxite Mines and Minerals Limited (J.V.C.) R/o - 404 Civil Lines Opp. Chief Minister House District Raipur, 492001
... Petitioner versus 1 - State of Chhattisgarh Through Secretary of Mines And Mineral Department Naya Raipur Mantralaya, 492002. 2 - Chhattisgarh Mineral Development Corporation Limited, Through Its Managing Director, Sector -24, Office Block -7a, 3rd Floor Nava Raipur Atal Nagar, Raipur Chhattisgarh. 3 - Union of India Through Secretary, Ministry of Mines, Add-3rd Floor, A Wing Shastri Bhawan, New Delhi 110001
... Respondents For Petitioner : Mr. Kishore Bhaduri, Senior Advocate along with Mr. Priyanshu Gupta, Advocate. For State : Mr. Prafull Bharat, Advocate General along with Mr. Kalpesh Ruparel, Panel Lawyer. For Respondent No. 2 : Mr. Yogesh Pandey, Advocate. (A) Relief sought:-
This petition has been filed by the petitioner for issuance of direction to the respondent authorities to deci
The judgment continues below.
Read the full judgment
A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.
The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.
Reproduced from the public record of the Chhattisgarh High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.