M/S M Venkata Rao Infra Projects PVT LTD vs. Bruhat Bengaluru Mahanagara Palike
Held
The Court held that the BBMP's insistence on a GST certificate is unsustainable in law. Compliance through GST returns, CA certificates, and audit reports is sufficient to establish discharge of GST liability.
Facts
The petitioner was awarded a work contract in 2015, which was partly executed before the GST regime (July 1, 2017) and partly after. The respondent BBMP withheld the differential tax amount, demanding a specific certificate from GST authorities for reimbursement.
Key Issues
Whether a GST certificate from authorities is mandatory for reimbursement of differential tax on works straddling pre and post-GST regimes? Is compliance via GST returns and CA certificates sufficient proof of tax discharge?
Sections Cited
Section 142(10), Section 31, Section 39
AI-generated summary — verify with the full judgment below
Cause title — parties, addresses and appearances
DATED 29.03.2025 BEARING NO. EE/PC- 2/PR/308/2024-25 ISSUED BY THE R-2 VIDE ANNEXURE-A AND ETC.
THIS WRIT PET
The judgment continues below.
Read the full judgment
A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.
The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.