M/S Bangalore Electricity vs. Sri H M Ramachandra

WA/121/2022HC KarnatakaGSTCNR KAHC01006628202222 August 2025Bench: S.G.PANDIT,T.M.NADAF21 pages
AI SummaryAllowed

Held

The Court held that the KERC's action in revising the commissioning time to six months and reducing the tariff was unreasonable, unfair, and arbitrary. The Court found that the PPA and subsequent communications from BESCOM clearly indicated an understanding that the project would be completed by December 31, 2016, and the project was indeed installed by September 30, 2016. The Court applied the principle of promissory estoppel, citing the Supreme Court's decision in ANDHRA PRADESH ELECTRICITY REGULATORY COMMISSION VS. R.V.K. ENERGY PRIVATE LIMITED, stating that the petitioners should not suffer due to the unreasonable stand taken by KERC. The Court also held that the contention regarding the availability of an alternative remedy was unsustainable at that stage, as the writ petition had been entertained and decided on merits. The ratio is that regulatory bodies are bound by the principle of promissory estoppel when parties alter their position based on promises or assurances, and once a writ petition is entertained on merits, the existence of an alternative remedy is generally not a ground to interfere.

Facts

The petitioners installed a Solar Rooftop Photo Voltaic (SRTPV) System of 1000 KWh capacity. They entered into a Power Purchase Agreement (PPA) with Bangalore Electricity Supply Company Ltd. (BESCOM) on December 31, 2015, to sell net energy exported at Rs. 9.56 per unit. The Karnataka Electricity Regulatory Commission (KERC) approved the PPA on April 28, 2016, subject to completion of the SRTPV system by December 31, 2016. BESCOM reiterated this deadline on August 19, 2016. However, KERC issued a show-cause notice on August 29, 2016, proposing to revise the commissioning time to six months and the tariff to Rs. 5.20 per KWh. The petitioners' explanation was rejected, and KERC passed an order on October 20, 2016, revising the completion time to six months and the tariff to Rs. 5.20 per KWh. A review petition was rejected on August 24, 2017. The petitioners filed writ petitions challenging these orders.

Key Issues

1. Whether the KERC could revise the commissioning time for the SRTPV system from the agreed period of one year (or December 31, 2016) to six months, and consequently revise the tariff, when the PPA and subsequent communications indicated a longer period and the project was installed within the original timeframe. This issue turns on the principle of promissory estoppel and the sanctity of contractual obligations. The petitioners argued that KERC's action was arbitrary and violated the principle of promissory estoppel, as they acted on the assurances given in the PPA and BESCOM's communications. They contended that the KERC could not revisit the terms agreed upon and approved, especially when the project was installed by September 30, 2016. The appellant (BESCOM) argued that the Solar Policy fixed a six-month period for commissioning and that the learned Single Judge should not have entertained the writ petition due to the availability of an alternative statutory remedy before the Appellate Tribunal.

Sections Cited

Section 4 of the Karnataka High Court Act, 1961

AI-generated summary — verify with the full judgment below

1

IN THE HIGH COURT OF KARNATAKA AT BENGALURU

DATED THIS THE 22ND DAY OF AUGUST 2025

PRESENT

THE HON'BLE MR. JUSTICE S. G. PANDIT AND THE HON'BLE MR. JUSTICE T.M.NADAF

WRIT APPEAL NO.95/2022 (GM-RES) C/W WRIT APPEAL NO.121/2022 (GM-RES)

W.A.NO.95/2022

BETWEEN:

M/S. BANGALORE ELECTRICITY SUPPLY COMPANY LTD., A COMPANY INCORPORATED UNDER THE PROVISIONS OF THE COMPANIES ACT, 1956 HAVING ITS CORPORATE OFFICE AT K R CIRCLE, BENGALURU-560 001 NOW REPRESENTED BY ITS GENERAL MANAGER (GST & PP (F & C))

...APPELLANT (BY SRI. RANGA SR. COUNSEL FOR SMT. SUMANA NAGANANAD, ADV.)

AND:

1.

SMT. JAIMALA W/O H.M. RAMACHANDRA R/AT 496, 6TH MAIN

2

DOLLARS COLONY BANGALORE-560094. 2. THE STATE OF KARNATAKA MINISTRY OF ENERGY ROOM NO.236, 2ND FLOOR VIKAS SOUDHA DR. B.R. AMBEDKAR VEEDHI BANGALORE- 560001 REP. BY PRINCIPAL SECRETARY.

3.

KARNATAKA ELECTRICITY

REGULATORY COMMISSION

A STATUTORY BODY UNDER THE PROVISIONS OF THE ELECTRICITY ACT, 2003

NOW AT NO.16, C-1 MILLER TA

The judgment continues below.

Read the full judgment

A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.

See plans and prices

The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.

Reproduced from the public record of the Karnataka High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.