N. Pramod Sibi vs. The State Of Kerala
Original PDF →IN THE HIGH COURT OF KERALA AT ERNAKULAM PRESENT THE HONOURABLE MR. JUSTICE P.V.KUNHIKRISHNAN TUE AY, THE 26TH DAY OF OCTOBER 2021 / 4TH KARTHIKA, 1943 WP(C) NO. 15459 OF 2021 PETITIONER: N. PRAMOD SIBI AGED 43 YEARS S/O. SUBRAMANYAN, ANDALATT HOUSE, KESERY COLLEGE ROAD, NORTH PARAVOOR, ERNAKULAM DISTRICT, PIN 683513 BY ADVS. MADHU RADHAKRISHNAN NELSON JOSEPH M.D.JOSEPH DEEPAK ASHOK KUMAR RESPONDENTS: 1 THE STATE OF KERALA DIRECTORATE OF INDUSTRIES AND COMMERCE, REPRESENTED BY ITS PRINCIPAL SECRETARY, VIKAS BHAVAN, 3RD FLOOR, UNIVERSITY OF KERALA, SENATE HOUSE CAMPUS, PALAYAM, THIRUVANANTHAPURAM, PIN 695 033 2 THE KERALA INDUSTRIAL INFRASTRUCTURE DEVELOPMENT CORPORATION (KINFRA), KINFRA HOUSE, T.C 31/2312, SASTHAMANGALAM, THIRUVANANTHAPURAM, PIN 695 010, REPRESENTED BY ITS MANAGING DIRECTOR. BY ADV P.U.SHAILAJAN SMT.VIDYA KURIAKOSE. GP THIS WRIT PETITION (CIVIL) HAVING COME UP FOR ADMISSION ON 26.10.2021, THE COURT ON THE SAME DAY DELIVERED THE FOLLOWING:
W.P.(C).No.15459/2021 2 P.V.KUNHIKRISHNAN, J. -------------------------------- W.P.(C).No.15459 of 2021 ---------------------------------------------- Dated this the 26th day of October, 2021 JUDGMENT The petitioner had applied for tender floated by the 2nd respondent to carry out the work of rectification of walkways (cable trench cover slabs) Phase II at KINFRA Apparel Park, Thumba, Thiruvananthapuram. The copy of the tender submitted by the petitioner is Ext.P1. The petitioner being the lowest tenderer, the 2nd respondent selected the petitioner to carry out the work. Ext.P2 conditional work order was issued by the 2nd respondent wherein two conditions were to be complied with for acceptance of the tender finally and also for signing the agreement. The first condition was that the petitioner should produce performance security deposit of Rs.2,18,127/-- and the second condition was that the petitioner should produce additional performance guarantee of Rs.2,05,569/-. The petitioner produced the performance
W.P.(C).No.15459/2021 3 security deposit of Rs.2,18,127/-. But, as far as the additional performance guarantee of Rs.2,05,569/- is concerned, the petitioner was not able to produce the bank guarantee, though he produced fixed deposit receipt for the same amount. However, since this was not acceptable to the 2nd respondent, there was no final acceptance of the tender by the 2nd respondent and consequently no agreement was signed nor the work site was handed over in the light of the same. Finally the work order was cancelled as per Ext.P3. However, as per Ext.P3, the petitioner has been informed that the performance security deposit of Rs.2,18,127/- will stand forfeited and further an additional liability of Rs.5,77,475/- has been imposed on the petitioner as cost. Aggrieved by the same, this writ petition is filed with following prayers: i. Issue a writ of Certiorari or any other writ calling for records leading to issuance of Exhibit P3 and Ext P6 and quash the same. ii. Declare that there is no binding contract between the Petitioner and the 2nd respondent. iii. Issue a writ of mandamus directing the 2nd respondent to return to the Petitioner the Treasury Fixed Deposit of Rs. 2,18,127/- submitted towards Performance Security Deposit. iv. Pass such other writ order or direction as this
W.P.(C).No.15459/2021 4 hon'ble court may deem fit and proper. v. Award the costs of the Writ Petition.
Heard the counsel for the petitioner and the Standing Counsel for the 2nd respondent. I also heard the Government Pleader.
The counsel for the petitioner reiterated his contentions in the writ petition. The first and foremost contention raised by the petitioner is that there is no concluded contract between the petitioner and the 2nd respondent and therefore, the direction in Ext.P3 to forfeit the performance security deposit and imposition of cost as additional liability is unsustainable. The counsel takes me through the relevant clauses in Ext.P4 General Conditions of Contract. The counsel also takes me through Ext.P2, the work order. According to the counsel for the petitioner, there is no agreement executed between the petitioner and the 2nd respondent and therefore, the forfeiture of the performance security deposit is unsustainable. The counsel also relied on the judgment of the Apex Court in Padia Timber Company (P) Ltd v. The Board of Trustees of Visakhapatnam Port
W.P.(C).No.15459/2021 5 Trust [2021 (3) SCC 24] and the judgment dated 23.07.2021 in Civil Appeal No.4358 of 2016 in South Eastern Coalfields Ltd. and Others v. S.Kumar's Associates AKM (JV) [MANU/SC/0473/2021]. The counsel also relied on the judgment of the Apex Court in State of Madhya Pradesh and Others v. Firm Gobardhan Dass Kailash Nath [AIR 1973 SC 1164].
The Standing Counsel for the 2nd respondent submitted that there is a concluded contract in the light of Ext.P2 work order. The Standing Counsel takes me through the contents in Ext.P2 and submitted that in Ext.P2 it is clearly stated that the date of commencement of the work shall be 10th day from the date of work order or 7th day from the date of receipt of work order whichever is earlier and the entire work shall be completed within six months. The Standing Counsel submitted that since there is an implied contract, and hence the forfeiture of the performance security deposit is perfectly justified. The Standing Counsel also relied on the judgment of the Apex Court in Jawahar Lal Barman v. Union of India [1962 KHC 468] and Dresser Rand S.A. v. Bindal Agro Chem Ltd [2006 KHC 79].
W.P.(C).No.15459/2021 6
The short point to be decided in this case is whether there is a concluded contract between the petitioner and the 2nd respondent, and whether the 2nd respondent is justified in forfeiting the performance security deposit and imposing additional liability as cost. Ext.P2 is the work order issued by the 2nd respondent. It will be better to extract Ext.P2 for a proper decision of the dispute: “ Mr. Pramod Sibi Andalatt House Keseri Road N. Paravur Ernakulam-683513 Sir, Sub: Rectification of walkways (cable trench cover slabs) Phase II at KINFRA International Apparel Park, Thumba, Trivandrum- Work order issuing of Ref: Tender No. KINFRA/KIAP/38/2019-20 With reference to the above, Mr. Pramod Sibi, Andalatt House, Keseri road, N. Paravur, Ernakulam, is hereby informed that your tender for the work of "Rectification of walkways (cable trench cover slabs) Phase II at KINFRA International Apparel Park, Thumba, Trivandrum" has been accepted at your quoted rates amounting to Rs.43,62,525/- (Rupees forty three lakhs sixty two thousand five hundred and twenty five only) which is 14.05% below the estimate
W.P.(C).No.15459/2021 7 PAC. The accepted schedule of work is the same as given in the tender. GST at applicable rates will be paid extra. You are directed to attend this office with Kerala stamp paper worth Rs.200/- along with Performance Security Deposit of Rs.2,18,127/- (Rupees two lakhs eighteen thousand one hundred and twenty seven only), being 5% of the contract amount (at least 50% of this shall be in the form of Treasury Fixed Deposit and the rest in the form of Bank Guarantee from a Scheduled/Nationalized bank) and execute an agreement with KINFRA within 4 weeks on receipt of the work order. The validity of the Bank Guarantee shall be up to the expiry of defect liability period plus three months. You are also requested to submit a bank Guarantee for Rs.2,05,569/- (Rupees two lakhs five thousand five hundred and sixty nine only) towards Additional Performance Guarantee, as per G.O (P) No. 19/2016/Fin dated 03/02/2016, for executing the agreement. The date of commencement of the work shall be 10
th day from the date of Work Order or 7
th day from the date of receipt of Work Order whichever is earlier and the entire work shall be completed within 6 months. You are requested to take over the site and start the work forthwith as per the terms and conditions of the tender. (underlines supplied) All other terms and conditions as per the tender shall be binding on you. The rates quoted by you shall
W.P.(C).No.15459/2021 8 remain firm till the completion of the work. Please return a copy of this work order duly signed as a token of your acceptance. Thanking you, Yours faithfully, Managing Director.”
A reading of Ext.P2 will show that the petitioner is directed to submit a bank guarantee for Rs.2,05,569/- (Rupees two lakhs five thousand five hundred and sixty nine only) towards additional performance guarantee as per the Government Order referred in it for executing the agreement. It is also mentioned that the petitioner should deposit performance security deposit of Rs.2,18,127/-, being 5% of the contract amount. Admittedly the petitioner was not able to pay the additional performance guarantee, as stated in Ext.P2. It is clear from Ext.P2 that the bank guarantee of Rs.2,05,569/- is towards the additional performance guarantee as per G.O.(P) No.19/2006/Fin dated 03.02.2016, for executing the agreement. Since the petitioner was not able to submit a bank guarantee for Rs.2,05,569/- towards additional performance guarantee, admittedly no agreement is executed
W.P.(C).No.15459/2021 9 between the petitioner and the 2nd respondent.
The Standing Counsel for the 2nd respondent takes me through Ext.R2(d). Ext.R2(d) is a letter from the petitioner to the Managing Director of the 2nd respondent. It will be better to extract the contents in Ext.R2(d): “To The Managing Director KINFRA INTERNATIONAL APPAREL PARK THUMBA, TRIVANDRUM Sir, Sub: Rectification of walkways (cable trench cover slabs) Phase 2 at KINFRA International Apparel Park, Thumba, Trivandrum. Ref. Tender No.KINFRA/KIAP/38/2019-20 Received the work order dated 14/02/2020 the security deposit /bank guarantee for this projects will be submitted and the work agreement will be executed at the earliest. Hereby enclosing the signed work order as a token of acceptance. Thanking You Regards Pramod Sibi Contractor”
W.P.(C).No.15459/2021 10
The Standing Counsel also takes me through Ext.R2(f), which is also a letter from the petitioner to the Managing Director of the 2nd respondent. The contents in Ext.R2(f) is also extracted hereunder: “To The Managing Director KINFRA INTERNATIONAL APPAREL PARK THUMBA, TRIVANDRUM Sub: Rectification of walkways (cable trench cover slabs) Phase II at KINFRA International Apparel Park, Thumba, Trivandrum. Ref. your letter KIN/V/KIAP/2020-21/731 Sir, Received your letter on 2/11/2020. First of all would like to extend my apology for the delay has occurred for starting the work mentioned above. As it is written in your letter, due to the pandemic Covid 19, I could not start the work on time. I would like to inform you that I will start the by the end of this month. I am very much interested to do the work.
Hence I request you to consider this as my final request for time extension and do the needful. Thanking you, Yours faithfully Pramod Sibi”
W.P.(C).No.15459/2021 11
Based on Exts.R2(d) and R2(f), the Standing Counsel for the 2nd respondent submitted that the petitioner accepted the work order and hence there is a concluded contract between the petitioner and the 2nd respondent. But, by going through the contents in Exts.R2(d), it is clear that the petitioner only informed the 2nd respondent that Ext.P2 work order is received and the security deposit/bank guarantee for the project will be submitted and the agreement will be executed at the earliest. It is true that in Ext.R2(f) the petitioner requested time to start the work. But from Ext.R2(d) it is clear that the work agreement is not executed as on that date and he only received the work order. He also stated in it that he will produce the security deposit/bank guarantee and will execute the work agreement at the earliest. Similarly Ext.R2(f) is also a letter based on another letter sent by the 2nd respondent on 02.11.2020. It is only a time extension petition to start the work. But it is an admitted fact that as on that date also, the second condition in Ext.P2 work order is not complied by the petitioner and no agreement is executed between the petitioner and the 2nd respondent.
W.P.(C).No.15459/2021 12
Subsequently Ext.P3 termination notice was issued by the 2nd respondent. Again it will be beneficial if the contents of Ext.P3 is perused and for that purpose, it is extracted hereunder: “TERMINATION NOTICE Sub: Contract for Rectification of Walkways (Cable Trench Cover Slab) Phase Il at KINFRA International Apparel
Parks
Ltd.,
Thiruvananthapuram- Termination Notice Ref:
Work Order No: KIN/V/KIAP/391/2019-21 dated 14th Feb 2020. 2. E mail sent by KIAP to the contractor dated 26th May 2020
Treasury savings No.JL No.0234585/ 799010100048811 dated 29/05/2020 4.Our letter No. KIN/V/2020-21/731 dated 28/10/2020 The subject work for Rectification of Walkways (Cable Trench Cover Slab) at KINFRA International Apparel Parks Ltd., Thiruvananthapuram was awarded to you for a total contract value of Rs.43,62,525/-, excluding GST as per work order first cited. Though the work was awarded to you, you have not come up to execute the Agreement after furnishing additional Bank Guarantee towards Security Deposit and you have also not commenced the work pursuant
W.P.(C).No.15459/2021 13 to the work order. You have promised to commence the work after furnishing the additional performance security and after executing the Agreement. Inspite of continuous contact from our officers you have not come forward to execute the Agreement. As per the work order the completion date of work is 22.08.2020. This was that you are not at all interested in executing the work. The delay in commencing the work has caused serious difficulties. You have given a final notice dated 28.10.2020 asking you to execute the agreement and commence the work within 10 days from the above letter indicating that if you fail to do so we would be constrained to cancel the work order and forfeit EMD and also work will be awarded to another agency at the risk and cost and any additional amount incurred in awarding the work to another agency will be recovered from the security by forfeiting fixed security deposit submitted by you. Clause 5 in General Conditions of Contract, it clearly states that "if the contractor commits default in the execution of work, KINFRA shall without prejudice to any other right or remedy available in law, be at liberty to cancel the work order & forfeit the performance guarantee absolutely". There is absolutely no response from you and we
therefore cancel the work order dated 14.02.2020 and will be carrying out the rectification work through another agency at your risk and cost. In that event any additional cost incurred by KINFRA will be
W.P.(C).No.15459/2021 14 recovered from the Security Deposit and EMD will be forfeited without further notice to you. Thanking you, Yours faithfully, Managing Director”
In Ext.P3, it is clearly stated that though the work was awarded to the petitioner, the petitioner has not executed the agreement after furnishing the additional bank guarantee towards security deposit and the petitioner has not commenced the work pursuant to the work order. It is also stated in the termination notice that the petitioner promised to commence the work after furnishing the additional performance security and after executing the agreement. It is clearly stated in Ext.P3 termination order that in spite of continuous contact from the office of the 2nd respondent, the petitioner has not come forward to execute the agreement. Even though final notice dated 28.10.2020 was issued to the petitioner to execute the agreement and commence the work within ten days, the petitioner did not execute the agreement. In such circumstances, there is nothing in Exts.P2 and P3 to show that there is a concluded contract between the petitioner
W.P.(C).No.15459/2021 15 and the 2nd respondent as far as the execution of the work is concerned. It is an admitted fact that, there is no work agreement executed between the petitioner and the 2nd respondent. It is true that in Ext.P2, it is stated that “please return a copy of this work order duly signed as a token of your acceptance” and thereafter the petitioner sent Ext R(2)(d). But R(2)(d) can’t be treated as an acceptance of an agreement to execute the work. At the maximum, it can be treated as an acceptance to perform the conditions in the work order like submission of Performance Security Deposit, Additional Performance guarantee and thereafter to execute the agreement itself. Therefore till an agreement to execute the work is entered between parties after performing the conditions in Ext.P2 work order, it can’t be said that there is a concluded contract.
The Apex Court in Padia Timber Company's case (supra) considered about this aspect in paragraphs 55 to 59 and the same is extracted hereunder:
“55. The trial court relied on Section 4 of the Contract Act, but completely overlooked Section 7. Section 7 of the Contract Act, 1872 is set out herein below for convenience:
W.P.(C).No.15459/2021 16 “7. Acceptance must be absolute.-In order to convert a proposal into a promise the acceptance must- (1) be absolute and unqualified; (2) be expressed in some usual and reasonable manner, unless the proposal prescribes the manner in which it is to be accepted. If the proposal prescribes a manner in which it is to be accepted, and the acceptance is not made in such manner, the proposer may, within a reasonable time after the acceptance is communicated to him, insist that his proposal shall be accepted in the prescribed manner, and not otherwise; but, if he fails to do so, he accepts the acceptance.”
It is a cardinal principle of the law of contract that the offer and acceptance of an offer must be absolute. It can give no room for doubt. The offer and acceptance must be based or founded on three components, that is, certainty, commitment and communication. However, when the acceptor puts in a new condition while accepting the contract already signed by the proposer, the contract is not complete until the proposer accepts that condition, as held by this Court in Haridwar Singh v. Bagun Sumbrui. An acceptance with a variation is no acceptance. It is, in effect and substance, simply a counter-proposal which must be accepted fully by the original proposer, before a contract is made.
In Union of India v. Bhim Sen Walaiti Ram, a three-Judge Bench of this Court held that acceptance of an offer may be either absolute or conditional. If
W.P.(C).No.15459/2021 17 the acceptance is conditional, offer can be withdrawn at any moment until absolute acceptance has taken place.
In Jawahar Lal Burman v. Union of India, referred to by the High Court, this Court held that under Section 7 of the Contract Act acceptance of the offer must be absolute and unqualified and it cannot be conditional. However, in the facts and circumstances of that case, on a reading of the letter of acceptance as a whole, the appellant's argument that the letter was intended to make a substantial variation in the contract, by making the deposit of security a condition precedent instead of a condition subsequent, was not accepted.
The High Court also overlooked Section 7 of the Contract Act. Both the trial court and the High Court overlooked the main point that, in the response to the tender floated by the respondent Port Trust, the appellant had submitted its offer conditionally subject to inspection being held at the Depot of the appellant. This condition was not accepted by the respondent Port Trust unconditionally. The respondent Port Trust agreed to inspection at the Depot of the appellant, but imposed a further condition that the goods would be finally inspected at the showroom of the respondent Port Trust. This condition was not accepted by the appellant. It could not, therefore, be said that there was a concluded contract. There being no concluded contract, there could be no question of any breach on the part of the
W.P.(C).No.15459/2021 18 appellant or of damages or any risk purchase at the cost of the appellant. The earnest deposit of the appellant is liable to be refunded.”
Similarly in South Eastern Coalfields' case (supra), the Apex Court considered this point in paragraph 19 and the same is also extracted hereunder:
“19. We have already reproduced aforesaid the terms of the letter of award and what it mandated the Respondent to do. None of the mandates were fulfilled except that the Respondent mobilized the equipment at site, handing over of the site and the date of commencement of work was fixed vide letter dated 28.10.2009. Interestingly this letter has been addressed to the Sub Area Manager of the Appellant by the office of the Appellant. The Respondent, thus, neither submitted the Performance Security Deposit nor signed the Integrity Pact. Consequently, the work order was also not issued nor was the contract executed. Thus, the moot point would be whether mobilization at site by the Respondent would amount to a concluding contract inter se the parties. The answer to the same would be in the negative.”
Moreover, in Firm Gobardhan Dass's case (supra), the Apex Court considered this point. Relevant paragraphs are 2,3 and 8 to 10:
“2. By a notice, dated August 27, 1953, the Chief
W.P.(C).No.15459/2021 19 Conservator of Forests invited tenders for the purchase of certain lac and lac products, the quantities whereof were set out therein. The conditions of sale, subject to which the said tenders were to be made, were as follows: x x x 5. 25 per cent of the purchase price shall be deposited in cash or G.C. notes immediately after the close of sale.-
The sanction of the Government of final bids will be given at the spot.
All lac purchased must be removed within one month and on full payment; credit will be given on 25 per cent deposit. The lac will remain at the godowns at the risk of the purchasers after the sales are finished.
In case of default of payment of balance within one month the 25 per cent deposit shall be forfeited and the Government may resell lac in which case loss not recovered by the deposit will be recovered from defaulters.... These conditions were announced at the time of the sale.
The respondent-firm submitted tenders for two areas, for Rs. 3,80,000 relating to Umaria Division and Rs. 7000/- for Chhatarpur Division. These tenders, being the highest, were accepted for and on
W.P.(C).No.15459/2021 20 behalf of the Chief Conservator of Forests. Though the respondent-firm had to deposit 25 per cent of the aforesaid two amounts, it deposited two sums only, namely, Rs. 7000/- and Rs. 500/- and asked for a week's time to pay the balance of the said 25 per cent initial deposit. xxx xxx xxx
The undisputed facts are that in response to the notice issued by the Chief Conservator the respondent firm offered their tenders for the purchase of the said forest products. Its tenders being the highest, they were accepted for and on behalf of the Chief Conservator. However, the tenders were, as aforesaid, made subject to the said conditions of sale and to such of the rules made by the then Rewa State as were applicable. Before the said tenders could be said to have ripened into a concluded contract, they had not only to be accepted but also sanctioned by the Chief Conservator for and on behalf of the State.
The conditions, subject to which the said tenders could be validly made, were that the person making such a tender had to deposit on the spot 25 per cent of the purchase price as the initial deposit and the final bid, if accepted, had to be sanctioned by the Chief Conservator at the spot. Condition 8 then provided that the balance of the price, that is to say, the remaining 75 per cent of such price, had to be
W.P.(C).No.15459/2021 21 paid within one month from the date of the purchase. If the person making the tender failed to pay the remaining balance of 75 per cent of the price, the State would be entitled to forfeit the initial deposit of 25 per cent and to resell the goods and recover the deficit, if any, from the purchaser. Conditions 5 and 6 were conditions of sale subject to which a tender could be validly accepted and sanctioned by the Chief Conservator. There was no proof, by way of anything in writing, to show that such a sanction was in fact given. There was equally no proof that the Chief Conservator had the authority to waive the conditions, subject to which only tenders could be validly accepted and sanctioned. In the absence of the initial deposit of 25 per cent of the purchase price having been made on the spot, the tenders could neither be validly accepted nor sanctioned by the Chief Conservator. In the absence of any authority to waive the said conditions, there was no valid acceptance or sanction of the said tenders. The true position, therefore, was that the offering of the said tenders by the respondent firm and their purported acceptance by the Forest authorities never ripened into a concluded contract. Further, the rules defined a forest contract and required that such a contract had to be in writing and in the prescribed form. It was contended that the prescribed form was such that such a contract could not fit in in any such form. That undoubtedly is so. But that only meant that the prescribed form would not apply, and would
W.P.(C).No.15459/2021 22 not mean that the rest of the rule requiring the contract to be in writing could not apply. It is not disputed that the contract in question was not in writing.
The conclusion that the offer and the purported acceptance of the said tenders did not result in a concluded contract is strengthened by a perusal of all the conditions of sale as a whole. When so read, they disclose that when a person offered a tender he had to deposit on the spot 25 per cent of the purchase price offered by him therein. The tender could not be accepted, much less sanctioned, unless such an initial deposit was made on the spot. Neither the said conditions nor the rules provided for waiving the condition of having to make the initial deposit of 25 per cent on the spot or for extending time for making such initial deposit. The next stage provided by the conditions was that the remaining balance of the price, that is, the remaining 75 per cent of the price, had to be paid within one month from the date of the acceptance and sanction of the tender. Condition 8, therefore, provided as a consequence of Condition 5, that in the event of default by the purchaser in payment of the remaining balance of 75 per cent of the price, the State would become entitled to forfeit the initial deposit of 25 per cent already made and to resell the goods in question and claim the difference between the contract price and the resale price. Such difference would become payable by reason of Rule 30(3)(e) and under Section
W.P.(C).No.15459/2021 23 82 of the Forest Act as arrears of land revenue. Condition 8 thus postulated that upon a tender being opened, but before it was accepted or sanctioned, the initial deposit was made by the would-be purchaser and upon such deposit having been made, the tender could be accepted and sanctioned resulting into a concluded contract and the person so making the tender would become the buyer of the goods. No rule or order was brought to our notice which permitted the Chief Conservator either to waive Condition 5 or to extend the time for making the initial deposit. Indeed, there could not be any such rule. The reason is that according to these conditions the balance of the price, that is, 75 per cent of the price remaining unpaid, had to be paid within one month and the goods had also to be taken delivery of and removed within that period. This can only happen if the initial deposit of 25 per cent was made on the spot and the tender was thereupon accepted and sanctioned on the spot. On such acceptance and sanction, the person whose fender was accepted would become the buyer, in whom property in goods would vest and who, therefore, would take delivery and pay the balance of the price within one month, and who in default of payment of the remaining 75 per cent of the price would become liable to lose the initial deposit of 25 per cent of the price deposited by him earlier when his tender was accepted.”
W.P.(C).No.15459/2021 24
In the light of the principle in the above judgments, it cannot be said that, there is any concluded contract between the petitioner and the 2nd respondent simply because the petitioner submitted Exts.R2(d) and R2(f) after Ext.P2 work order. Of course the Standing Counsel relied on the judgment of the Apex Court in Jawahar Lal Barman's case (supra) and Dresser Rand's case (supra). The counsel relied on paragraph 16 in Jawahar Lal Barman's case (supra). On a reading of paragraph 16 of the above judgment, it is clear that the facts in that case is different from the facts in the present case. In that case, in the letter issued on 31.08.1949 which is extracted in paragraph 16, it is clearly stated that the contract is concluded by this acceptance and a formal acceptance of tender will follow immediately on receipt of treasury receipt. There is no such case to the 2nd respondent that any information is sent to the petitioner to the effect that there is a concluded contract. Similarly in the decision in Dresser Rand's case (supra), the relevant paragraphs relied on by the Standing Counsel for the 2nd respondent is paragraphs 39 and 40. I think the facts in that case has no relevance to the facts in the present case. The facts in that
W.P.(C).No.15459/2021 25 case will show that, in the letter of intent, it was requested to start the work with a stipulation that the detailed contract would be drawn up later. No such stipulation is there in Ext.P2 work order.
In the light of the principles laid down by the Apex Padia Timber Company's case (supra), South Eastern Coalfields' case (supra) and Firm Gobardhan Dass's case (supra), I think there is no concluded contract between the petitioner and the 2nd respondent to forfeit the performance security deposit or to impose cost because there is absolutely no agreement executed between the petitioner and the 2nd respondent.
The Standing Counsel for the 2nd respondent drew my attention to the following clause in Ext.P4: “A sum of Rs........... has been deposited in prescribed manner as Earnest Money Deposit (EMD). If I/We, fail to furnish the prescribed performance guarantee within prescribed period, I/We agree that KINFRA shall without prejudice to any other right or remedy, be at liberty to forfeit the said earnest money absolutely. Further, if I/We fail to commence work as specified, I/We agree that KINFRA shall without prejudice to any other right or remedy available in law, be at liberty to forfeit the said performance
W.P.(C).No.15459/2021 26 guarantee absolutely. The said Performance Guarantee shall be a guarantee to execute all the works referred to in the tender documents upon the terms and conditions contained or referred to those in excess of that limit at the rates to be determined in accordance with the provision contained in Clause 12.2 and 12.3 of the tender form.”
But the petitioner has got a case that he has not signed such a statement. The relevant portion of the averments in the writ petition is extracted hereunder: “The 2nd respondent claims certain conditions of contract apply even at the time of issuance of the tender form and this according to them form a part of the tender documents. Aof the relevant portion of the General Conditions of Contract (KINFRA 7/8) (e-TENDER) is produced herewith and marked as Exhibit P4. Even though the same has not been signed or executed or submitted by the Petitioner, the 2nd respondent claims the same to be a part of the tender document.
The relevant portion of Ext. P4 which according to the 2nd respondent forms a part of the tender documents clearly states as follows: "A sum of Rs........... has been deposited in the prescribed manner as Earnest Money Deposit (EMD). If I/we, fail to furnish the prescribed performance guarantee within the prescribed period, I/we agree that KINFRA shall without prejudice to
W.P.(C).No.15459/2021 27 any other right or remedy, be at liberty to forfeit the said earnest money absolutely". In the present case, the additional performance guarantee/Bank Guarantee has not been submitted by the petitioner as prescribed by the 2nd respondent. In the said event, the remedy of the 2nd respondent is only to forfeit the EMD alone and not the security deposit. Hence the petitioner is entitled to get back the amounts already paid to the 2nd respondent towards the Security Deposit amount. The relevant extract of General Conditions of Contract which would have formed a part of the agreement, if signed is produced as Exhibit P4(a).”
There is no denial of the above statement by the 2nd respondent. In such circumstances, the averments in the writ petition has to be accepted. Therefore, the petitioner succeed and writ petition is to be allowed. Therefore, this writ petition is allowed in the following manner:
All further proceedings consequent to Exts.P3 and P6 are quashed.
It is declared that there is no concluded contract between the petitioner and the 2nd respondent based on Ext.P2 work order.
The 2nd respondent is directed to return to the
W.P.(C).No.15459/2021 28 petitioner the treasury fixed deposit of Rs.2,18,127/-
submitted
towards
the performance security deposit, within three weeks from the date of receipt of a copy of this judgment. P.V.KUNHIKRISHNAN JV JUDGE
W.P.(C).No.15459/2021 29 APPENDIX OF WP(C) 15459/2021 PETITIONER EXHIBITS Exhibit P1 AOF THE TENDER SUBMITTED BY THE PETITIONER BEFORE THE 2ND RESPONDENT Exhibit P2 AOF THE LETTER DATED 14-2- 2020 ISSUED BY THE 2ND RESPONDENT TO THE PETITIONER Exhibit P3 AOF THE TERMINATION NOTICE ISSUED BY THE 2ND RESPONDENT DATED 13- 01-2021 Exhibit P4 AOF THE RELEVANT PORTION OF THE GENERAL CONDITIONS OF CONTRACT (KINFRA 7/8) E-TENDER) Exhibit P4 AOF THE RELEVANT EXTRACT OF GENERAL CONDITIONS OF CONTRACT WHICH IS CLAIMED BY RESPONDENT NO. 2 TO BE APPLICABLE Exhibit P5 AOF THE LEGAL NOTICE DATED 26-2-2021 ISSUED BY THE PETITIONER TO THE 2ND RESPONDENT. Exhibit P6 AOF THE LEGAL REPLY NOTICE DATED 30-03-2021 ISSUED BY THE 2ND RESPONDENT TO THE PETITIONER. RESPONDENT EXHIBITS Exhibit R2(A)OF THE RELEVANT PAGES OF THE NOTICE INVITING TENDER DATED 25/11/2019 ISSUED BY THE KINFRA Exhibit R2(B)OF THE ITERM RATE BILL OF QUANTITIES (BOQ) ISSUED BY THE KINFRA Exhibit R2(C)OF THE ITEM RATE BOQ SUBMITTED BY THE PETITIONER Exhibit R2(D)OF THE LETTER DATED 23/02/2020 SENT BY THE PETITIONER TO THE 2ND RESPONDENT Exhibit R2(E)OF THE LETTER DATED 26/05/2020 ISSUED BY THE RESPONDENT NO.2 TO THE PETITIONER Exhibit R2(F)OF THE LETTER 09/11/2020 SENT BY THE PETITIONER TO 2ND RESPONDENT Exhibit R2(G)OF THE RELEVANT PAGES OF THE GENERAL CONDITIONS OF CONTRACT ISSUED
W.P.(C).No.15459/2021 30 BY KINFRA Exhibit R2(H)OF THE BOQ SUBMITTED BY THE CONTRACTOR SRI.K. UNNIKRISHNAN Exhibit R2(I)OF THE LETTER DATED 28/10/2020 SENT KINFRA TO THE WRIT PETITIONER. // P.A.to Judge
Reproduced from the public record of the Kerala High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.