Propel Developers PVT LTD vs. Manoj Nautamlal Gandhi

Original PDF →
IA/13865/2025HC BombayGSTCNR HCBM01059904202507 January 20266 pages
AI SummaryPartly Allowed

Facts

Propel Developers Pvt Ltd (the appellant/petitioner) is challenging two orders of the Appellate Tribunal. The core dispute involves an additional consideration of Rs. 10,85,000/- and GST of Rs. 1,30,200/- demanded by the promoter due to an alleged increase in carpet area. The allottees (respondents) are Mikunj Kiran Joshi and Manoj Nautamlal Gandhi. The appellant argues that a different bench of the Appellate Tribunal, with one common member, had previously ruled in a similar case concerning the same project that the allottee was liable for this additional consideration and GST. Furthermore, the appellant contends that interest for delayed possession should only be payable until the offer of possession, not until actual delivery. The impugned orders directed the promoter to refund the additional consideration and GST with interest, and also to pay interest for delayed possession until actual delivery.

Held

The High Court admitted the second appeals, framing substantial questions of law. Regarding the interim applications, the Court partly allowed them, staying the execution of the impugned orders subject to conditions. The Court noted that there was no controversy over the liability to pay interest for delayed possession from January 1, 2016, to April 1, 2018, and that the Appellate Tribunal had recorded no change in the area of the flats. The Court also acknowledged that one Honorable Member was part of both the impugned judgment and a previous judgment in a similar case concerning the same project. This prior judgment had held the allottee liable for the additional consideration and GST and restricted the promoter's interest liability for delayed possession until the date of offer of possession. The Court found that the entitlement to refund and interest for delayed possession up to actual delivery warranted consideration. The conditions for the stay included the promoter depositing the additional consideration and GST before the Appellate Tribunal, and paying interest on the consideration amount from January 1, 2016, to April 1, 2018, at the specified rate within one month.

Key Issues

1. Whether, in identical fact situations for the same project, one bench of the Appellate Tribunal can issue a contrary judgment on the liability of an allottee to pay additional consideration for increased carpet area and the promoter's liability for interest on delayed possession, especially when one member is common to both benches, and if so, whether the failure to follow the earlier view or refer to a larger bench vitiates the impugned judgment (turning on principles of judicial discipline and consistency)? 2. Whether the promoter's liability to pay interest for delayed possession ceases two months after the offer of possession, and if so, whether the Appellate Tribunal erred in directing interest payment until actual possession (turning on the interpretation of Section 18 of RERA, 2016 and contractual terms)? Contentions: Petitioner/Appellant (Propel Developers Pvt Ltd): Argued that a prior decision of the Appellate Tribunal in a similar case, involving the same project and one common member, held the allottee liable for the additional consideration and GST. They also contended that interest for delayed possession should be limited to the period until the offer of possession was made, citing the earlier judgment. They relied on the principle of consistency in judicial pronouncements. Respondent/Allottee: The judgment does not record specific arguments from the respondents regarding the issues framed. However, the impugned orders, which they are defending, directed refund of additional consideration and GST with interest, and interest for delayed possession until actual delivery.

Sections Cited

Section 18

AI-generated summary — verify with the full judgment below

Cause title — parties, addresses and appearances
37&47-SA588-2025+.DOC Santosh IN THE HIGH COURT OF JUDICATURE AT BOMBAY CIVIL APPELLATE JURISDICTION SECOND APPEAL NO. 588 OF 2025 WITH INTERIM APPLICATION NO. 13746 OF 2025 IN SECOND APPEAL NO. 588 OF 2025 Propel Developers Pvt Ltd ...Appellant Versus Mikunj Kiran Joshi …Respondent WITH SECOND APPEAL NO. 586 OF 2025 WITH INTERIM APPLICATION NO. 13865 OF 2025 IN SECOND APPEAL NO. 586 OF 2025 Propel Developers Pvt Ltd ...Petitioners Versus Manoj Nautamlal Gandhi …Respondent Mr. Vikramjit Garewal, a/w Abir Patel (through VC) and Protyusha Thanawala, i/b Wadia Ghandy & Co, for the Appellant in both Appeals. Mr. Jairam Chandnani (through VC), a/w Shraddha Jadhav, i/b Lexim Associates, for the Respondent in both the Appeals. CORAM: N. J. JAMADAR, J. DATED: 7th JANUARY, 2026 PC:- SA/588/2025 and SA/587/2025 1. Heard the learned Counsel for the parties. 1/6 SANTOSH SUBHASH KULKARNI Digitally signed by SANTOSH SUBHASH KULKARNI Date: 2026.01.07 18:08:56 +0530 37&47-SA588-2025+.DOC 2. The following substantial questions of law arise for consideration: (i) Whether in respect of one and the same project and in matters arising out of identical facts-situation, one Bench of the Appellate Tribunal could take a contrary view on the aspect of the liability of the allottee to pay additional consideration upon purported increase in the carpet area, and the liability of the promoter to pay interest for the delay in delivery of possession, till the actual delivery of possession or only till the date of offer of delivery of possession, when one Honorable Member is a part of both the Benches, and, if not, whether failure to follow the earlier view or refer the matter to a larger Bench, vitiated the impugned judgment and order? (ii) Whether in the facts and circumstances of the case, the liability of the promoter to pay interest for the delayed delivery of possession of the subject flat, came to an end after two months of the offer to deliver the possession and, thus, the Appellate Tribunal was in error in directing the Promoter to pay interest till the actual delivery of possession? 3. Admit. 2/6 37&47-SA588-2025+.DOC 4. Issue notice to the respondent. 5. Mr. Chandnani, the learned Counsel, waives notice for the respondent. 6. The appellant shall file private paper-book within a period of eight weeks. 7. The appeals be listed for final hearing on 18th March, 2026. IA/13746/2025 and IA/13865/2025 8. The second appeals have been admitted by framing substantial questions of law. 9. These interim applications have been preferred seeking stay to the execution and operation of the impugned orders passed by the Appellate Tribunal thereby directing the applicant - promoter to refund the additional amount of consideration of Rs.10,85,000/- and GST of Rs.1,30,200/- along with interest at the rate of State Bank of India’s Highest Marginal Cost Leading Rate (MCLR) plus 2% interest, from the date of respective payment till realization and interest under Section 18 of the Real Estate (Regulation and Development) Act, 2016 (“RERA, 2016”) on the amount paid by the allottee towards consideration from 1st January, 2016 till the date of handing over physical 3/6 37&47-SA588-2025+.DOC possession of the respective flat to the allottee, at the State Bank of India’s MCLR plus 2% within 30 days of the said order. 10. In another appeal being Appeal No.AT0006000000052847 in respect of the very same project and arising out of identical facts-situation, another Bench of the Appellate Tribunal by a judgment and order dated 31st January, 2023, has held that the allottee in the said case was liable to pay the said additional consideration of Rs.10,85,000/- and GST Rs.1,30,200/- on account of increase in the carpet area and restricted the liability of the promoter to pay interest for the delayed delivery of possession from 1st January, 2016 till 11th July, 2018, the date the possession was offered to be given to the allottee. One Honorable Member was a party to both the impugned judgment and the judgment in Appeal No.AT0006000000052847. 11. In the aforesaid view of the matter, the question of entitlement of the respondents/allottees to the refund of the additional consideration alongwith interest, and interest for the delayed period of possession up to the date of actual physical delivery of possession, warrants consideration. 12. Since there is not much controversy over the liability to pay interest for the delayed delivery of possession from 1st January, 2016 to 1st April, 2018 and, in the impugned order, the 4/6 37&47-SA588-2025+.DOC Appellate Tribunal has categorically recorded that there has been no change in the area of the subject flats initially offered to be sold and the area shown in the revised sanctioned plan, and no additional area has been allotted to the allottee, this Court considers it necessary to put the applicant/promoter to terms while staying the execution and operation of the impugned

judgment and order.

13.

Hence, the following order: : O R D E R: (I) The applications stand partly allowed. (II) The execution, operation and implementation of the impugned common judgment and order is stayed till final hearing of the appeals subject to the following conditions: (a) The applicant promoter shall deposit the amount of additional consideration of Rs.10,58,000/- and GST Rs.1,30,200/- before the Appellate Tribunal, within a period of one month from today. (b) The applicant promoter shall pay interest under Section 18 of the RERA, 2016 on the amount of consideration paid by the respondent allottee in respect of the respective subject flats from 1st January, 2016 to 1st April, 5/6

37&47-SA588-2025+.DOC 2018 at the rate of State Bank of India’s MCLR plus 2%, within one month from today. (c) In the event of default, the Authorities under RERA, 2016 shall be at liberty to enforce the order of the Appellate Tribunal, in accordance with law. Applications disposed. [N. J. JAMADAR, J.] 6/6

Reproduced from the public record of the Bombay High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.