M/S Aditya Birla Fashion And Retail LTD vs. Dayanand
Facts
M/s Aditya Birla Fashion and Retail Ltd. (appellant) leased a warehouse from Dayanand (respondent) for nine years from May 1, 2016, at a monthly rent of INR 10,00,000, with a 5% escalation annually. The lease deed stipulated that the lessor (respondent) would insure the premises against fire and other perils, while the lessee (appellant) would insure its own goods. On October 16, 2018, a fire occurred, causing significant damage to the warehouse and the appellant's stored goods. The respondent received an insurance claim of INR 2,52,39,404/-. The appellant had also insured its stocks. The appellant exercised its right under Clause 14 of the lease deed to terminate the lease with three months' prior notice and rent payment. An arbitration proceeding ensued, and the Arbitral Award dated December 23, 2023, directed the appellant to pay rent beyond the termination date. The appellant challenged this award under Section 34 of the Arbitration and Conciliation Act, 1996, before the Exclusive Commercial Court, which rejected the objection. The appellant then filed an appeal under Section 37 of the Act.
Held
The Court held that the Arbitrator erred in awarding rent for the period after the termination of the lease. Clause 14 of the Lease Deed clearly provided the lessee (appellant) with an unqualified right to terminate the lease by giving three months' prior written notice, which the appellant had exercised. The Arbitrator could not have allowed the respondent to continue receiving rent beyond the termination date, as this would amount to rewriting the contract, which was beyond the Arbitrator's jurisdiction. The Court found that the Arbitrator's finding of negligence on the part of the appellant was contrary to the evidence, as the fire was caused accidentally due to a short circuit. The Court also noted that the respondent had received an insurance claim for the fire incident, and any further claims for actual losses should have been pursued against the insurer. The Commercial Court, in rejecting the appellant's Section 34 objection, failed to address these critical aspects and acted in a routine and mechanical manner. Therefore, the appeal was allowed, the order of the Commercial Court was set aside, and the arbitral award was quashed.
Key Issues
1. Whether the Arbitrator erred in awarding rent to the claimant/respondent for the period post the termination of the lease agreement by the appellant under Clause 14 of the Lease Deed, considering the appellant had provided three months' prior written notice and paid the rent for that period? 2. Whether the Commercial Court, while adjudicating the objection under Section 34 of the Arbitration and Conciliation Act, 1996, failed to properly consider the express terms of the contract, specifically Clause 14, which granted the lessee an unqualified right to terminate the tenancy? Contentions of the Appellant: The appellant argued that the Arbitrator exceeded its jurisdiction by awarding rent beyond the lease termination date, as Clause 14 of the lease deed unequivocally granted the lessee the right to terminate the lease with three months' notice, which was duly exercised. The appellant contended that the Commercial Court failed to exercise its jurisdiction by not addressing this crucial aspect and mechanically rejecting the Section 34 objection. The appellant also argued that the Arbitrator's findings on negligence were contrary to evidence and that the Arbitrator had gone beyond the pleaded case. Contentions of the Respondent: The respondent argued that the Arbitrator's award was based on the evidence and the contract, and that the Commercial Court had correctly upheld the award. The respondent contended that the appellant's negligence caused the fire and that the appellant was liable for rent until the premises were re-let. The respondent relied on the Arbitral Award and the Commercial Court's order.
Sections Cited
Section 37, Section 34
AI-generated summary — verify with the full judgment below
IN THE HIGH COURT OF PUNJAB AND HARYANA AT CHANDIGARH
FAO-CARB No. 39 of 2025 (O&M) Reserved on: 14.11.2025. Date of pronouncement: 13.02.2026
M/s ADITYA BIRLA FASHION AND RETAIL LIMITED ...Appellant(s)
V/s DAYANAND
...Respondent(s)
CORAM: HON'BLE MR. JUSTICE ASHWANI KUMAR MISHRA
HON'BLE MR. JUSTICE ROHIT KAPOOR
Argued by: Mr. Aashish Chopra, Senior Advocate, assisted by
Mr. Vijender Parmar, Advocate,
Ms. Rupa Pathania, Advocate, and
Mr. Yash Pal Sharma, Advocate for the appellant.
Mr. Sumeet Mahajan, Senior Advocate, assisted by
Mr. Saksham Mahajan, Advocate,
Mr. Shrey Sachdeva, Advocate, and
Ms. Radhika Dekshay Advocate, for respondent.
****
Date when order was reserved 14.11.2025
Date of Pronouncement of order 13.02.2026
Date of uploading of order 16.02.2026
Whether operative part or full order is pronounced Full
Delay, if any, in pronouncing of full order and reasons thereof. NA
ASHWANI KUMAR MISHRA, J.
Juri iction of this Court under Section 37 of the Arbitration and Conciliation Act, 1996 (for short ‘the Act of 1996’) is invoked by M
The judgment continues below.
Read the full judgment
A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.
The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.
Reproduced from the public record of the Punjab and Haryana High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.