Deen Bandhu Chotu Ram Thermal Power Plant Hpgcl Yamuna Nagar vs. M/S Green Vision Testing And Enviro Services

ARB/6/2025HC Punjab and HaryanaGSTCNR PHHC01002780202517 March 2026Bench: MR. JUSTICE JASGURPREET SINGH PURI15 pages
AI SummaryAllowed

Facts

The petitioner, Deen Bandhu Chotu Ram Thermal Power Plant (HPGCL) Yamuna Nagar, filed a petition under Section 11(6) of the Arbitration and Conciliation Act, 1996, seeking the appointment of a sole arbitrator. The dispute arose from an offer made by the respondent, M/s Green Vision Testing and Enviro Services, which was accepted by the petitioner on January 25, 2022, followed by a work order issued on February 7, 2022. The work order contained an arbitration clause. The petitioner invoked this clause by issuing a notice on April 4, 2024, proposing arbitrator names, but the respondent denied the existence of an arbitration agreement. The respondent's primary objection was that a formal contract agreement, stipulated in condition No.1 of the work order, was never executed, thus violating the terms and rendering the petition non-maintainable.

Held

The Court held that the existence of an arbitration agreement is to be examined prima facie under Section 11(6-A) of the Arbitration and Conciliation Act, 1996. The Court referred to settled legal position, including pronouncements from the Supreme Court, emphasizing that the scope of examination at the reference stage under Section 11 is limited to the prima facie existence of an arbitration clause and its invocation. Any allegations of breach of contract or other conditions are matters to be adjudicated by the arbitrator. The Court found that the conditions for appointing an arbitrator under Section 11 were satisfied, as an arbitration clause was present in the work order, and the petitioner had invoked it. The respondent's objection regarding the non-execution of a formal contract agreement was deemed a substantive dispute for the arbitrator to decide. Consequently, the Court allowed the petition and nominated a retired District and Sessions Judge as the Sole Arbitrator.

Key Issues

1. Whether an arbitration agreement exists between the parties within the meaning of Section 7 of the Arbitration and Conciliation Act, 1996, despite the non-execution of a formal contract agreement as stipulated in condition No.1 of the work order? 2. Whether the petitioner is entitled to the appointment of a sole arbitrator under Section 11(6) of the Act, considering the respondent's contention of breach of contract due to the non-execution of a formal agreement? Petitioner's arguments: The petitioner contended that an arbitration agreement exists as per Section 7(4) of the Act, citing the exchange of offer and acceptance, and the presence of an arbitration clause in the work order, even without a separately signed formal contract. They argued that the non-execution of a formal agreement does not preclude the existence of an arbitration agreement. Respondent's arguments: The respondent argued that the non-execution of the contract agreement within 7 days of the work order, as required by condition No.1, constituted a breach of contract. They asserted that this violation made the petition under Section 11 of the Act unsustainable and liable for dismissal.

Sections Cited

Section 11(6), Section 7, Section 7(3), Section 7(4), Section 11(6-A), Section 12, Section 16, Section 29-A

AI-generated summary — verify with the full judgment below

ARB-6-2025 (O&M) 1 IN THE HIGH COURT OF PUNJAB & HARYANA

AT CHANDIGARH

ARB-6-2025 (O&M)

Date of Decision:17.03.2026 Deen Bandhu Chotu Ram Thermal Power Plant HPGCL Yamuna Nagar

......Petitioner Versus M/S Green Vision Testing and Enviro Services ......Respondent CORAM: HON'BLE MR. JUSTICE JASGURPREET SINGH PURI Present:- Mr. Prateek Mahajan, Advocate for the petitioner. Dr. Deepak Jindal, Advocate for the respondent. ***** JASGURPREET SINGH PURI J.(Oral)

1.

The present is a petition filed under Section 11 (6) of the Arbitration and Conciliation Act, 1996 (hereinafter referred to as ‘the Act’), seeking appointment of a sole arbitrator in the present case.

2.

Learned counsel for the petitioner submitted that vide Annexure A-2, the offer given by the respondent for the work was accepted by the petitioner on 25.01.2022, and on the basis of the aforesaid acceptance, an allotment letter/work order was issued to the respondent vide Annexure A-3 dated 07.02.2022. The said work order contains an arbitration clause at condi

The judgment continues below.

Read the full judgment

A free account opens 10 full GST judgments a month (one account works on both bharattax.net and this site). Re-reading one you have already opened does not count again.

See plans and prices

The summary, the parties, the sections and the citations above are open to everyone and always will be. Only the text of the order and the PDF are metered.

Reproduced from the public record of the Punjab and Haryana High Court. Verify against the court's own copy before relying on it. Income tax judgments are on bharattax.net.